I-205 auxiliary lanes |
Description: The project is located near the City of Tracy in San Joaquin County. The project will construct auxilairy lanes at 4 locations.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Joaquin |
City | Tracy |
Zip Code | 95304, 95376, 95377 |
Senate District |
05 |
Assembly District | 15, 17 |
Congressional District | 11 |
Caltrans District |
10 |
County/State Route | San Joaquin 205 |
Postmile Begin/End | 1.9 6.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 3150 | 2,066 |
Lane Miles Added (Mixed) | 12 | 12 |
Peak Period Time Savings (minutes) | 125440 | 82,255 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Melissa Ramos | (209) 941-1963 | melissa.ramos@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Melissa Ramos | (209) 941-1963 | melissa.ramos@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Melissa Ramos | (209) 941-1963 | melissa.ramos@dot.ca.gov | |
Construction Phase |
Department of Transportation | Melissa Ramos | (209) 941-1963 | melissa.ramos@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Melissa Ramos | (209) 941-1963 | melissa.ramos@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$25,000 | $-15,930 | $9,070 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$26,660 | $-13,721 | $12,939 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $51,660 | $-29,651 | $22,009 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,169 | $0 | $1,169 | $1,582 | |||
Design(PS&E) |
$4,830 | $0 | $4,830 | $3,790 | |||
Right of Way |
$1,250 | $0 | $1,250 | $60 | |||
Construction |
$44,411 | $-29,651 | $14,760 | $13,676 | |||
Total* | $51,660 | $-29,651 | $22,009 | $19,108 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/01/2007 05/01/2009 |
|
01/01/2007 11/25/2008 |
100 | 10/01/2007 11/25/2008 |
-9 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2009 05/01/2010 |
|
11/25/2008 05/03/2010 |
100 | 11/25/2008 06/09/2009 |
0 11 |
|
Begin Right of Way Phase
End Right of Way Phase |
05/01/2009 05/01/2010 |
|
11/25/2008 05/03/2010 |
100 | 04/24/2009 05/03/2010 |
-5 0 |
|
Begin Construction Phase
End Construction Phase |
10/01/2010 04/01/2013 |
|
10/01/2010 04/01/2013 |
100 | 11/02/2010 03/04/2013 |
-1 1 |
|
Begin Closeout Phase
End Closeout Phase |
10/01/2014 11/01/2014 |
|
10/01/2014 11/01/2014 |
100 | 10/01/2013 02/13/2015 |
12 -3 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 07/01/2009 | 07/01/2009 | 100 | 05/25/2010 | -11 | ||
Implementation Date | 11/01/2009 | 11/01/2009 | 0 | 06/25/2010 | -8 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 3150 | 2,066 |
Lane Miles Added (Mixed) | 12 | 12 |
Peak Period Time Savings (minutes) | 125440 | 82,255 |
Bond Funding Cost | |
---|---|
Adopted: |
$25,000,000 |
Current Approved: |
$9,070,000 |
Actual Expenditures: |
$7,951,000 |
Status as of December 31, 2023.