Caltrans Logo

I-205 auxiliary lanes

Description: The project is located near the City of Tracy in San Joaquin County. The project will construct auxilairy lanes at 4 locations.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Tracy
Zip Code 95304, 95376, 95377
 
Senate District
05
Assembly District 15, 17
Congressional District 11
 
Caltrans District
10
 
 
County/State Route San Joaquin 205
Postmile Begin/End 1.9 6.8
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  3150    2,066  
Lane Miles Added (Mixed)  12    12  
Peak Period Time Savings (minutes)  125440    82,255  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Right of Way Phase
Department of Transportation Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Construction Phase
Department of Transportation Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$25,000 $-15,930 $9,070
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$26,660 $-13,721 $12,939
Non Budgeted ETC
$0 $0 $0
 
Total**** $51,660 $-29,651 $22,009

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,169 $0 $1,169 $1,582
Design(PS&E)
$4,830 $0 $4,830 $3,790
Right of Way
$1,250 $0 $1,250 $60
Construction
$44,411 $-29,651 $14,760 $13,676
 
Total* $51,660 $-29,651 $22,009 $19,108

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2007 

05/01/2009 
 

 
01/01/2007 

11/25/2008 
100  10/01/2007 

11/25/2008 
-9 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2009 

05/01/2010 
 

 
11/25/2008 

05/03/2010 
100  11/25/2008 

06/09/2009 


11 
Begin Right of Way Phase

End Right of Way Phase
05/01/2009 

05/01/2010 
 

 
11/25/2008 

05/03/2010 
100  04/24/2009 

05/03/2010 
-5 

Begin Construction Phase

End Construction Phase
10/01/2010 

04/01/2013 
 

 
10/01/2010 

04/01/2013 
100  11/02/2010 

03/04/2013 
-1 

Begin Closeout Phase

End Closeout Phase
10/01/2014 

11/01/2014 
 

 
10/01/2014 

11/01/2014 
100  10/01/2013 

02/13/2015 
12 

-3 
Corridor System Management Plan
Adoption Date 07/01/2009    07/01/2009  100  05/25/2010  -11 
Implementation Date 11/01/2009    11/01/2009  06/25/2010  -8 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 3150 2,066
Lane Miles Added (Mixed) 12 12
Peak Period Time Savings (minutes) 125440 82,255

Bond Funding Cost
Adopted:
$25,000,000
Current Approved:
$9,070,000
Actual Expenditures:
$7,951,000

 

Status as of December 31, 2023.